Cost to Complete Management Tool for Sage 100 Contractor

The Syscon Cost to Complete Management Tool allows a project manager to make cost to complete projections by cost code and cost type at any time during the lifetime of the job. The projections are then “aged” from the date the projection was made as more costs are collected for the specific cost code and type. “As of” reports can be printed for any period of the job.

For example, if the concrete subcontract is projected to take an additional $10,000 to complete on a job from March, and there are $2,500 worth of costs in April, the projection is automatically adjusted in April to indicate $2,500 of costs to-date and the projection to complete is now $7,500 (as of April).